Light Reading
The aftermath of Superstorm Sandy brings the issue of back-up battery power for mobile cell cites into focus

Sandy: The Case for Better Cell Site Backup?

Dan Jones
LR Mobile News Analysis
Dan Jones, Mobile Editor
11/2/2012
50%
50%

The wireless devastation wrought by Superstorm Sandy may be reason to re-evaluate the amount of battery backup power available to commercial cell sites after a major disaster.

Light Reading Mobile spoke to a public safety network expert at the 4G World show in Chicago this week who suggested one reason why some networks maintained connection through the brunt of the storm but went dead the next day was inadequate backup battery power.

"After Katrina, the FCC mandated eight-hour battery backup on cell sites," Emil Olbrich, lead project engineer for the office of law enforcement standards at the National Institute of Standards and Technology, reminded us.

That, though, was just the start of a long struggle between the regulator and the industry.

The backup power battle
The Federal Communications Commission (FCC) started an inquiry into communication failures after Katrina in 2006 and mandated the change in early 2007. The CTIA and mobile operators kicked back against the ruling, arguing that it would cost hundreds of millions of dollars to add eight-hour battery backup to 200,000 cell sites across the U.S.

The FCC made some concessions on the ruling in 2008 but generally stuck to its guns. The CTIA, Sprint Corp. (NYSE: S) and others took the ruling to the United States Court of Appeals for the District of Columbia Circuit, asking for a stay from the ruling.

There's a good summary of these events in this Powergrid International article from 2008.

The court declared the case "unripe" in July 2008 because the Office of Management and Budget ("OMB") hadn't examined the ruling. The CTIA requested the OMB reject the FCC mandate in October 2008.

The White House office, which has oversight of federal regulations, rejected the rule in November 2008 because the FCC failed to get public comment on it. The FCC could have tried to overturn that decision but decided not to in December 2008.

The FCC said back then it would revise the ruling but didn't give a timescale for those actions.

The issue was raised again in 2011 when, following tropical storm Irene, Connecticut State Senator Andrew Roraback said he would introduce legislation to make operators equip towers with backup generators. The industry described the measures as unnecessary and unrealistic.

After Sandy?
At the 4G show, Olbrich noted that many commercial cell sites currently have less backup time than eight hours.

Verizon Wireless , however, did tell the Associated Press on Oct. 29 that all of its cell sites have eight hours or more of backup battery power.

Industry attendees we spoke to at the 4G World show agreed that battery backup had kicked in after the storm but then simply ran out. In such instances, carriers have to bring in generators or mobile cell sites to bring coverage back while the power is out.

Clearly, in a storm the size of Sandy it's difficult and dangerous to try and undertake that in the immediate aftermath of the storm's impact. The entire process is also a costly one for operators, as they have to send workers to the sites to prepare them for power availability once the grid comes back.

Obviously -- as we have reported -- backup power is by no means the only cell site issue in a storm of this magnitude. Many sites have also suffered major water damage, wind damage or simply been overloaded by the volume of traffic from concerned users trying to reach friends and loved ones.

All the major carriers are providing blow-by-blow updates of their efforts to bring the networks online.

As of 10 a.m. ET Thursday, the number of cell site outages in areas affected by the storm had fallen from about 25 percent to 19 percent, according to the FCC.

The public safety angle
Still, NIST engineer Olbrich says the kind of backup capabilities available on commercial networks would not pass muster on the nationwide first-responder LTE network being funded to the tune of $2 billion (of a total projected $7 billion) by the federal government.

"For public safety, well, it's just not good enough," Olbrich said of backup at commercial sites.

For more
For continuing updates on the state of communications following the superstorm, see Hurricane Sandy Updates.

— Dan Jones, Site Editor, Light Reading Mobile

(10)  | 
Comment  | 
Print  | 
Newest First  |  Oldest First  |  Threaded View
year2525
50%
50%
year2525,
User Rank: Light Beer
1/22/2013 | 9:37:42 PM
re: Sandy: The Case for Better Cell Site Backup?
-áInteresting stuff, thanks for your input on this.
191Jack
50%
50%
191Jack,
User Rank: Light Beer
1/22/2013 | 8:57:29 PM
re: Sandy: The Case for Better Cell Site Backup?
The generators we used at our sites were either natural gas or propane. in the case of propane we buried all the tanks we could along with the fuel lines. All our tanks were set up for a minimum of 5 days continuous run time. In every case of an emergency, it gave us ample time to clear a path to a site and get a fuel truck in. We never ran out of gas. The other thing we did was to clear all the trees growing outside our sites so that any outdoor generators were not damaged although many of our sires had generators inside the cell building. The buildings were precast concrete and none were ever damaged in an emergency.

Our only use of diesel powered generators was at our switches and a few portable generator sets that could be brought in in case of a generator failure. We also had 365/24/7 generator service contracts and regular preventative maintenance. We ran every generator including our switch units on Tuesday, Wednesday, or Thursday under full site and switch loads during the very busiest times of the day to make sure they would do the job when needed.
191Jack
50%
50%
191Jack,
User Rank: Light Beer
1/22/2013 | 8:39:57 PM
re: Sandy: The Case for Better Cell Site Backup?
I retired after 23 years with a NE US cellular carrier. From day 1 we not only had battery backup at our cell sites and switches but also generators. To me and the carrier I worked for at the time it was unthinkable not to provide continuous backup power as our subscribers needed their phones more during an emergency.-á
In 1985 we had a hurricane that put our rival carrier OUT OF SERVICE because the power outage was several days. We stayed on line except for one site where the leased tower we were on was blown down.-á
I've seen carriers pour money into portable generators and control centers, but for naught as the generators could not be dispatched to the sites that needed them when the crisis hit.-á
I'm afraid I find the carriers argument pretty weak about the cost if they are going to serve the public interest. Their loss of revenue in these cases should be cause for alarm.-á
If anyone is interested I have plenty more to say but I am not going to bore the people that won't listen.-á
Kit Kilgour
50%
50%
Kit Kilgour,
User Rank: Light Beer
12/5/2012 | 5:18:16 PM
re: Sandy: The Case for Better Cell Site Backup?


I can see that there is a stronger case for ensuring that macro-cell sites have significant amounts of backup power - the physical size of the site, mast and cabinet allows this. As the world moves towards more and more cell sites, this will become more challenging - small cells are designed to fit into small spaces, as well as some indoor ones even being powered over the ethernet, and some with both power supply and backhaul not under the full control of the operator.


It would seem that some mandate for backup power should be limited by e.g. the maximum transmit power of the cell, and the obligation on the operator to provide reasonable coverage, even if they had to limiting peak data rates in order to keep user capacity up with a smaller number of cells 

joset01
50%
50%
joset01,
User Rank: Light Beer
12/5/2012 | 5:18:15 PM
re: Sandy: The Case for Better Cell Site Backup?


How well small cells would survive a major storm and be managed after was also a question at the 4G World show. I asked Cisco's Kelly Ahuju about that.

krishanguru143
50%
50%
krishanguru143,
User Rank: Light Beer
12/5/2012 | 5:18:11 PM
re: Sandy: The Case for Better Cell Site Backup?




The problem with generators is that they are either going to run on a gas such as natural or propane or a liquid like gasoline or diesel.  Natural gas is not everywhere, how many homes in the Northeast still use heating oil?  So with the lack of natural gas in places, that leaves propane, gasoline or diesel.  The remaining three all have issues.  The pipes for propane could be damaged in a storm and leak propane fuel out; you also have an issue of refilling the tank after a storm.  The same holds true for gasoline and diesel, when the tank is empty, the tower is shutdown and you have to find a way to get the tank refilled.  That is easier said than done as the tower may not be accessible; downed trees, flooding, etc.  Carriers typically have portable generators and the site techs will drive let the generator charge the batteries backup and then move to the next site.  When you have a large number of sites that need attention, you don’t have the manpower or the generators to cover all of them.  It can take several hours or more to charge the batteries back up; so if it took four hours, the most you could do is less than six in any period unless you had multiple generators and then you might be able to get around twelve to eighteen.  Even that is not going to cut it, the techs are working non-stop.  Even with onsite generators, nothing says they would survive the storm either.  You also have that gasoline and diesel does go bad by just sitting in a tank.  Sure you can put fuel stabilizer in it; it still is not a good long-term solution.

Why not look at the power companies not be able to provide power.  Isn’t that really the issue?




krishanguru143
50%
50%
krishanguru143,
User Rank: Light Beer
12/5/2012 | 5:18:10 PM
re: Sandy: The Case for Better Cell Site Backup?




Power being out causes more problem than just mobile phone service.  Hospitals, grocery stores, fuel stations, water.  If someone has electric water heater, electric stove/oven and their fridge is obviously electric, good luck with food.  You better have MRE’s or something else.

 

That is why I said there is no real solution.  There is more everyone can do but just looking at mobile carriers to get their cards in order is very unfair.  The wireless carriers could pool together and have one generator per site for all the carriers there, but you still run into natural gas availability issues or fuel going bad or having to refill the tanks before they are empty.  Taking a hit a 8 hours after the storm is no different than a hit the day following.  An outage is an outage.

Probably why you won’t see power companies being asked to fix their infrastructure, some are municipality owned and the government would never do anything that would cost them money, they would make sure they would be excluded.  Asking the power companies to fix their infrastructure would also mean rate increases and that would never be popular either.  The telcos are a sitting duck.




joset01
50%
50%
joset01,
User Rank: Light Beer
12/5/2012 | 5:18:10 PM
re: Sandy: The Case for Better Cell Site Backup?


So you're proposing fixing the power grid as a more realistic solution? Okay then...


The point is that many commercial sites have very limited backup. I don't think anyone is expecting the networks not to take a hit in this situation but its not like we haven't had storms in the North-East recently.


I do wonder why companies don't put more power lines underground though. I get that it is initially cheaper but for how long if you need to keep fixing them?

joset01
50%
50%
joset01,
User Rank: Light Beer
12/5/2012 | 5:18:10 PM
re: Sandy: The Case for Better Cell Site Backup?


I don't disagree that the grid and fuel utilities should be fixed.


But it's not like the carriers aren't also benefiting from a shared nationwide resource as well. Often to great profits.

vz 29.5
50%
50%
vz 29.5,
User Rank: Light Beer
12/5/2012 | 5:18:09 PM
re: Sandy: The Case for Better Cell Site Backup?


Until we use a multi-fuel source generator such as a solar, wind turbine ,nat gas,220v,with a hand crank so we may take turns spinning the generator at each site,we may have to live within our eras limitations.How boring.Yours for site advancement.A malibu son.

Educational Resources
sponsor supplied content
Educational Resources Archive
Flash Poll
LRTV Documentaries
Sprint's Network Evolution

7|24|14   |   14:59   |   (0) comments


Sprint's Jay Bluhm gives a keynote speech at the Big Telecom Event (BTE) about Sprint's network and services evolution strategy, including Spark.
LRTV Documentaries
BTE Keynote: The Software-Defined Operator

7|24|14   |   18:43   |   (1) comment


Deutsche Telekom's Axel Clauberg explains the concept of the software-defined operator to the Big Telecom Event (BTE) crowd.
Light Reedy
Numbers Are In: LR's 2014 Salary Survey

7|24|14   |   1:25   |   (2) comments


Our fourth annual Salary Survey paints a picture of who's hiring, firing, earning, and yearning for a change in the telecom industry.
LRTV Custom TV
Driving the Network Transformation

7|23|14   |   4:29   |   (0) comments


Intel's Sandra Rivera discusses network transformation and how Intel technologies, programs, and standards body efforts have helped the industry migration to SDN and NFV.
LRTV Custom TV
Distributed NFV-Based Business Services by RAD

7|18|14   |   5:38   |   (0) comments


With the ETSI-approved Distributed NFV PoC running in the background, RAD's CEO, Dror Bin, talks about why D-NFV makes compelling sense for service providers, and about the dollars and cents RAD is putting behind D-NFV.
LRTV Custom TV
MRV – Accelerating Packet Optical Convergence

7|15|14   |   6:06   |   (0) comments


Giving you network insight to make your network smarter.
LRTV Custom TV
NFV-Enabled Ethernet for Generating New Revenues

7|15|14   |   5:49   |   (0) comments


Cyan's Planet Orchestrate allows service providers and their end-customers to activate software-based capabilities such as firewalls and encryption on top of existing Ethernet services in just minutes.
LRTV Custom TV
Symkloud NVF-Ready Video Transcoding, Big Data

7|9|14   |   3:41   |   (0) comments


Kontron and ISV partner Vantrix demonstrate high-performance video transcoding and data analytic solutions on same 2U standard platform that is ready for SDN and NFV deployments made by mobile, cable and cloud operators.
LRTV Huawei Video Resource Center
The Evolving Role of Hybrid Video for Competitive Success

7|4|14   |   4:09   |   (0) comments


At Huawei's Global Analysts Summit in Shenzhen, China, Steven C. Hawley from TV Strategies speaks to us about the evolving role of hybrid video for competitive success.
LRTV Huawei Video Resource Center
How CSPs Leverage Big Data in the Digital Economy

7|4|14   |   4:48   |   (2) comments


Justin van der Lande from Analysys Mason shares with us his views on how telecom operators can leverage customer asset monetization with big data. His discusses the current status of big data applications and the challenges and opportunities for telecom operators in the digital economy era.
LRTV Huawei Video Resource Center
Accelerator for Digital Business – Future Oriented BSS

7|4|14   |   3:08   |   (0) comments


Mobile and internet are becoming intertwined; IT and CT are integrating; and leading CSPs have begun to transform to information service and entertainment providers. How should the BSS system evolve to enable this transformation? Karl Whitelock, an analyst at Frost & Sullivan, shares his views.
LRTV Huawei Video Resource Center
Orange Tunisia Discusses Multi-Band Antenna With EasyRET Solution

7|4|14   |   2:45   |   (0) comments


As new site acquisition becomes more difficult, Orange Tunisia has requested multi-band antenna to support UMTS and LTE innovation. Some things considered include reducing the cost of antenna maintenance and having high reliability antenna and EasyRET solution.
Upcoming Live Events!!
September 16, 2014, Santa Clara, CA
September 16, 2014, Santa Clara, CA
October 29, 2014, New York City
November 11, 2014, Atlanta, GA
December 9-10, 2014, Reykjavik, Iceland
Infographics
Allot's latest MobileTrends Charging Report shows that value-based pricing plans are up from 35% in 2011 to 85% in 2014.
Today's Cartoon
Vacation Special Caption Competition Click Here
Latest Comment
Hot Topics
Microsoft to Axe 12,500 Ex-Nokia Employees
Sarah Reedy, Senior Editor, 7/17/2014
The Municipal Menace?
Jason Meyers, Senior Editor, Utility Communications/IoT, 7/22/2014
GM: 10 Car Models on Road With AT&T's LTE
Dan Jones, Mobile Editor, 7/18/2014
Cisco Puts a Fog Over IoT
Sarah Reedy, Senior Editor, 7/23/2014
Apple Earnings: Strong iPhone Sales, iPad Sales Slump, $7.8B Profit
Mitch Wagner, West Coast Bureau Chief, Light Reading, 7/22/2014
Like Us on Facebook
Twitter Feed